Integrated Piping & Duct Installation Success
By maintaining high-quality standards, completing thousands of welds with zero rejects, and efficiently managing resources, ParFab successfully met all key milestones. The result was a seamless, problem-free startup, demonstrating ParFab's reliability and expertise in overcoming the client’s challenges while ensuring optimal project performance.
Massive Installation
Completed 15,210 feet of ductwork, combining horizontal and vertical sections up to 66 inches in diameter, across 3,084 spools.
Expanded Scope
Due to exceptional quality, the project scope grew to include 17,050 feet of carbon steel piping and 2,208 feet of stainless steel piping, totaling 8,643 welds.
Complex Equipment
Installed 3 tanks, 3 heat exchangers, and over 1,545 devices, including valves and meters.
Peak Workforce
Grew from 34 to 142 crew members by project peak, including day and night shifts.
Zero Incidents
Achieved almost 500,000 man-hours with zero OSHA recordables, maintaining excellent safety and environmental standards.
Project Background
In September 2022, we received a call from our client stating that they needed a contractor to install ductwork and within 5 days, ParFab’s leadership team was onsite with client to determine how we could support. We mobilized in October 2022 with a crew of 47, ready to safely install the duct. The installation was completed successfully with 15,210 feet of ductwork.
Due to the success resulting from efficiencies and the quality of supporting the initial ductwork scope, we received a request to further support the project. The subsequent scope awarded to us involved piping installation. This led us to support multiple scopes and extended our presence on the project until the end of 2023.
Our team installed a total of 15,210 feet of ductwork, consisting of 6,820 feet of horizontal duct and 8,390 feet of vertical duct, ranging in size from 10 inches to 66 inches, totaling 3,084 spools of duct. Additionally, 17,050 feet of carbon steel piping was installed, ranging in sizes from ¼ inch to 30 inches, totaling 8,643 welds. Furthermore, 2,208 feet of stainless-steel piping was installed, ranging in sizes from ¾ inch to 6 inches, totaling 394 welds. In addition to the piping, 3 tanks, 3 heat exchangers, and over 1,545 devices, including valves, strainers, pumps, flow devices, temperature and pressure meters were also installed.
Industry
Semiconductor
Project Scope
HVAC & Piping
Project Challenge
Our client was behind schedule on their capital project and was in need of a qualified contractor to install ductwork with a quick turnaround.
How We Helped
Within 15 days of the initial meeting, ParFab was onsite to begin the ductwork installation. We installed 17,050 feet of carbon steel piping and 2,208 feet of stainless steel piping, along with other components, positioning them as a top contractor and securing future opportunities with the client.
Manpower
The workforce and PFS personnel needed to complete the project.
Crew Expansion Timeline
The ParFab team started with 19 boilermakers, 11 pipe fitters, and 4 welders, growing to 85 crew members by mid-December. At its peak, the team reached 142 crew members working on-site across day and night shifts.
0
Total # of Boilermakers
0
Total # of Pipe Fitters
0
Total # of Welders
0
Total # of Personnel
Health, Safety, & Environmental
This project peaked at 142 ParFab employees and 4 subcontractors with 88 employees. ParFab had 1 safety supervisor and 2 safety techs on days and 1 safety supervisor on night with 35 ParFab employees, 2 subcontractors with 24 employees. The total project completed almost 500,000 manhours with zero OSHA recordables.
-
PFS Man Hours
Number of Hours | 250,925
Percentage of Project Completed | 100% -
PFS Safety
Safe Behaviors
Total Number | 213,200
Rate | 97.79%
At-Risk Behaviors
Total Number | 47
Rate | 2.21%
Near Misses
Total Number | 11
Rate | 8.77%
First Aids
Total Number | 1
Rate | 0.80%
Other Incidents
Total Number | 0
Rate | 0%
OSHA Recordables
Total Number | 0
TRIR | 0% -
PFS Environmental
Total Number of Issues | 0
Rate | 0% -
PFS + Subcontractor Man Hours
Total Project Hours | 354,600
Percentage of Project Completed | 100% -
PFS + Subcontractor Safety
Safe Behaviors
Total Number | 384,395
Rate | 97.61%
At-Risk Behaviors
Total Number | 92
Rate | 2.39%
Near Misses
Total Number | 23
Rate | 12.97%
First Aids
Total Number | 3
Rate | 1.13%
Other Incidents
Total Number | 1
Rate | 0.56%
OSHA Recordables
Total Number | 0
TRIR | 0% -
PFS + Subcontractor Environmental
Total Number of Issues | 0
Rate | 0%
Having used numerous web themes over the years, I can confidently say that this theme stands out in its class. Not only is it aesthetically pleasing and highly customizable, but it's also intuitive and user-friendly. The responsive design adapts flawlessly to all devices, ensuring a seamless experience for our audience. Kudos to the team for creating such a top-notch product!
SANDA CAMBEL
DIRECTOR OF MARKETING
Project Quality and KPI Overview
This project was overseen by 1 quality manager, 3 Certified Welding Inspectors (CWIs), and 4 quality technicians. Key performance indicators (KPIs) included the installation of 1,545 pieces of equipment, 7,350 flange makeups, and 246 hydro tests, all completed at 100% with zero startup leaks. The team installed 17,050 linear feet of carbon steel piping, 2,208 linear feet of stainless steel piping, and 15,210 feet of ductwork. A total of 8,643 welds were made with zero rejects, reflecting the project’s exceptional quality and efficiency.
-
Total Flange Makeups
Total # of Equipment Installed | 1,545
Completion Rate | 100%
Total # of Flange Makeups | 7,350
Completion Rate | 100%
Total # of Hydro’s | 246
Completion Rate | 100%
Total # of Start-Up leaks | 0
Rate | 0% -
Piping Installed
Linear FT Carbon | 17,050
Completion Rate | 100%
Linear Ft of Stainless | 2,208
Completion Rate | 100%
Duct Work | 15,210
Completion Rate | 100% -
Large Equipment Installed
Tanks/ Vessels | 3
Completion Rate | 100%
Exchangers | 3
Completion Rate | 100% -
Weld History Report
Total Welds Made | 8,643
Total Welders | 34
Total Rejects | 0
Rate | 0%